0%

Unpacking The Energy Gap Beneath Zimbabwe’s Beneficiation Drive

By Clive Masarakufa
On September 01, 2026
Industry Insights
ERT 5 MINUTES
Blog Details Image

Last month we explored a fundamental and timely question. Who finances the smelters, the refineries and the concentrators that government’s own instruments have now made mandatory? Part of the answer to it has since become apparent. Lithium producers have already pledged US$1.45B for further processing infrastructure. The Bankers Association of Zimbabwe says local banks are already syndicating to fund plants of that size. There is, however, another fundamental question that very few people are asking out loud. Every one of those plants runs on electricity which Zimbabwe does not currently generate enough of. Who then generates more of it to make it sufficient? That is the second investable gap to unpack. It is the one that decides whether the first one ever closes. Let us discuss more.

The Demand Curve Has Already Turned

Speaking at Mine Entra 2026 on 30 July, the Chamber of Mines of Zimbabwe chief executive Isaac Kwesu highlighted some notable figures. Mining currently consumes approximately 1000MW. That is more than half of all the electricity produced locally. He expects sector demand to exceed 1500MW within twelve months. The demand driver he named was not new mines; rather, it is expansion and new beneficiation facilities. It gets interesting if you now set that against supply.

Installed generation capacity is about 2640MW. Dependable capacity ranges between 1200MW and 1600MW. Average supply spans between 1200MW and 1400MW against peak national demand of roughly 1800MW. An interesting insight emerges when you marry those two sets of figures. At 1500MW, mining alone would absorb the entirety of the dependable grid. Every household, farm, factory and hospital would be competing for what remains. That is not a warning about some distant future, rather, it is imminent.

The Minister Maintains The Deadline Is Still Set

On 17 July 2026 the Minister of Mines and Mining Development, Dr Polite Kambamura, refused a request from the Lithium Producers Association. They had asked to shift the lithium concentrate export ban from 1 January 2027 to the middle of 2027. He was unambiguous, “For now, we are not talking about the waiver. We are still sticking to the 1st of January.”

Consider what that date now requires as a key point to note. Prospect Lithium Zimbabwe’s US$400M sulphate plant at Arcadia is operating and exported Africa’s first locally produced lithium sulphate in April 2026. Sinomine is constructing a US$500M sulphate facility at Bikita Minerals. Kamativi Mining Company is developing a lithium sulphate project of more than US$200M. In 2025 the country exported 1.128M tonnes of spodumene concentrate for approximately US$513.8M. From January that volume must be converted inside Zimbabwe. That conversion is primarily an energy problem before we even talk of the metallurgy.

What The Shortfall Is Already Costing

Zimbabwe spent US$881.7M on electricity imports between January 2021 and March 2026. Roughly 20 percent of national requirements is drawn from Cahora Bassa in Mozambique, Eskom in South Africa and ZESCO in Zambia. Those suppliers deliver between 200MW and 400MW. In the first quarter of 2026 alone the import bill was US$35.1M.

Producers are paying in output as well as in dollars. Mimosa reported 6E concentrate down 6 percent to 239 100 ounces for the year to 30 June 2026. They cited intermittent power interruptions as well as difficult geology. The difference in consequence is noteworthy. An operating mine that loses power loses ounces. A new processing plant that loses power misses a statutory deadline. The second failure is considerably more expensive than the first.

The Market Has Already Answered & Still Is Answering

Watch where energy capital is going in this market. Zimplats commissioned a 35MW solar plant alongside its smelter expansion at the Selous Metallurgical Complex. They then committed a further US$54M to a second phase. Kamativi Mining Company is targeting September commissioning of 36MW of solar with 48MWh of battery storage at about US$25M, under a 25-year generation licence issued by the Zimbabwe Energy Regulatory Authority (ZERA). Eureka gold mine has energized the first 5.4MW of a planned 16.4MW. Blanket has 12.2MW.

The larger tier is coal. At Mine Entra on 6 August 2026, William Gambiza of the Coal Producers Association of Zimbabwe counted fourteen thermal projects targeting about 4860MW. Titan Power is 720MW of thermal plus 200MW of solar at US$1B, targeted for completion by the end of 2028. Prestige Massive pairs 1200MW with a chrome smelting plant at Beitbridge at US$1.4B. The Palm River energy and metallurgical special economic zone pair a two million tonne per year ferrochrome smelter with a 1200MW power complex. Notice what almost none of this is; it is not generation being built into the national grid for general supply. Rather, it is generation being built next to the load that needs it.

Why Behind The Meter Is Bankable When Grid Scale Has Not Been

Zimbabwe’s grid connected independent power producer pipeline has underperformed for reasons that are well documented. There are power purchase agreements financiers will not accept. There is currency risk on local currency payments. There is no sovereign guarantee. There is also licensing and tendering friction. Not one of those obstacles concerns whether the sun shines or the coal is there.

Now compare the two structures. A grid scale plant sells to a single utility offtaker, and that offtaker’s tariff and payment record become the entire credit question. A captive plant at a smelter sells to an exporter earning hard currency, under a mandate that gives it a statutory reason to keep processing. Change the offtaker and you change the credit. That is the crux of it.

Regulation has also moved in the same direction. Cabinet approved a new energy governance framework in 2026. It includes Own-Consumption Licensing Regulations formalizing generation for self-use, and Backbone Infrastructure Provision Regulations opening high voltage transmission to private participation. A ministry official put the expectation more bluntly at Africa Chromium Week 2026. If you want to process chrome at scale in Zimbabwe, you bring power into the mix.

What The Core Implications Of All This Are

You need to stop modelling electricity as just an operating cost line. Rather, in this market, regard it as a second asset; it must be structured like one. Build your processing case as two projects.

The plant carries its own capital stack and the generation carries another. Recall the tiering we discussed in March. A captive solar or thermal plant with a defined industrial offtaker and predictable cash flows is well suited for debt financing. A processing plant still in construction, with feed risk open, is not. The energy component is also where concessional and blended capital is most likely to fit since it carries a measurable development outcome.

Then you sequence the two. An energization date that lands after your commissioning date is a failed project with a working plant inside it. Build capacity headroom above nameplate demand rather than sitting exactly on it. There are now two feasibility questions in any beneficiation case in Zimbabwe. Where does the feed come from, and where does the power come from? An investment case that investors will take seriously is one that answers both questions.

Our Role As IHC

At IHC we are profiling opportunities in this sector as paired assets rather than single ones. When a processing venture enters our pipeline, we test the energy case with the same seriousness as the metallurgical one. We look at the generation licence, the offtake structure between plant and power, the construction sequence against the commissioning date, and the tariff assumption sitting underneath the model. We do this because we know exactly where the due diligence will spotlight.

Opportunity owners holding a processing concept should consider this as an invitation. The power component is itself an opportunity that can be brought to market, structured and funded on its own terms. In several cases it is the more bankable half of the venture.

At Investor Hosting Centre (IHC), our thrust is to bridge the gap between capital and credible, investment-ready projects. Our primary focus is on driving economic development in Zimbabwe and across Africa. Are you ready to put capital to work in Zimbabwe, bring an opportunity to market, or offer your services into our pipeline? Kindly go to investorhosting.com to sign up as an investor, opportunity owner or service provider. For more information you can email on info@investorhosting.com or call +2638677010683.

Let's accelerate your investment journey together.

We have projects in cities across diverse economies to choose from!

©2026 IHC - All Rights Reserved | Terms of Use | Privacy